FRANKLIN, Ind. — The City of Franklin Board of Public Works and Safety has approved a noise ordinance variance to allow nighttime construction along the US 31 corridor to help secure the route for winter travel.
Milestone Contractors presented the request to allow overhead signal and signage work between 7 p.m. and 7 a.m.
Construction on Phase 3 has fallen behind its original August 1 completion deadline. Due to extensive utility relocation delays across the corridor, final phase completion has been pushed back to June 2027.
To mitigate further delays and improve safety before winter weather sets in, Milestone has implemented weekday overtime and Saturday shifts. The approved evening hours will enable crews to complete overhead spans and signal work over US 31 with minimal disruption to daytime traffic.
City of Columbus finishes dam removal ahead of schedule on East Fork White River
Franklin Police solve 20-year-old murder case
Forbes recognizes BCSC as 'Best School District in Indiana'
City of Columbus approves municipal insurance renewals with minor rate changes
Columbus advances Rocky Ford Road traffic signal modernization project